<iati-activities version="2.03" generated-datetime="2026-11-23T14:42:54"><iati-activity xml:lang="en" default-currency="USD" last-updated-datetime="2026-11-20T19:29:57" hierarchy="1"><iati-identifier>44000-P114154</iati-identifier><reporting-org ref="44000" type="40"><narrative  xml:lang="en">World Bank</narrative></reporting-org><title xml:lang="en"><narrative>Thailand Public Sector DPL</narrative></title><description type="2" xml:lang="en"><narrative><![CDATA[]]></narrative></description><description type="1" xml:lang="en"><narrative><![CDATA[]]></narrative></description><participating-org role="1" ref="44001" type="40" xml:lang="en"><narrative>International Bank for Reconstruction and Development</narrative></participating-org><participating-org role="3" ref="44001" type="40" xml:lang="en"><narrative>International Bank for Reconstruction and Development</narrative></participating-org><activity-status code="3" /><activity-date type="1" iso-date="2009-02-26"><narrative>Planned start date of the activity</narrative></activity-date><activity-date type="2" iso-date="2010-11-18"><narrative>Actual start date of the activity</narrative></activity-date><activity-date type="3" iso-date="2013-06-30"><narrative>Planned end date of the activity</narrative></activity-date><activity-date type="4" iso-date="2013-06-30"><narrative>Actual end date of the activity</narrative></activity-date><contact-info type="1"><organisation><narrative>The World Bank</narrative></organisation><person-name><narrative>Mathew A. Verghis</narrative></person-name><telephone>+1-202-473-1000</telephone><email>mverghis@worldbankgroup.org</email><email>pic@worldbank.org</email><mailing-address><narrative>The World Bank, 1818 H Street, NW, Washington, DC 20433 USA</narrative></mailing-address></contact-info>

<recipient-country code="TH" percentage="100"><narrative xml:lang="en">THAILAND</narrative></recipient-country><location>
                <location-reach code="1" />
                <location-id vocabulary="G1" code="1609350" />
                <name><narrative>Bangkok</narrative></name>
                <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
                <pos>13.75398 100.50144</pos>
                </point>
                <exactness code="2"/>
                <location-class code="2" />
            </location><sector vocabulary="1" code="15126" percentage="25" xml:lang="en"/><sector vocabulary="1" code="15117" percentage="25" xml:lang="en"/><sector vocabulary="1" code="25010" percentage="25" xml:lang="en"/><sector vocabulary="1" code="51010" percentage="25" xml:lang="en"/><sector vocabulary="99" vocabulary-uri="http://pubdocs.worldbank.org/en/538321490128452070/Sector-Taxonomy-and-definitions.pdf" code="YZ" percentage="8.00000000" xml:lang="en"><narrative>FY17 - Other Industry, Trade and Services</narrative></sector><sector vocabulary="99" vocabulary-uri="http://pubdocs.worldbank.org/en/538321490128452070/Sector-Taxonomy-and-definitions.pdf" code="BC" percentage="92.0000000" xml:lang="en"><narrative>FY17 - Central Government (Central Agencies)</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000243" percentage="33" xml:lang="en"><narrative>MSME Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000041" percentage="17" xml:lang="en"><narrative>Public Finance Management</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000243" percentage="33" xml:lang="en"><narrative>MSME Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000111" percentage="1" xml:lang="en"><narrative>Fiscal sustainability</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000024" percentage="33" xml:lang="en"><narrative>Enterprise Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000072" percentage="3" xml:lang="en"><narrative>Rural Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000431" percentage="17" xml:lang="en"><narrative>Administrative and Civil Service Reform</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000112" percentage="1" xml:lang="en"><narrative>Public Expenditure Policy</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000043" percentage="34" xml:lang="en"><narrative>Public Administration</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000432" percentage="17" xml:lang="en"><narrative>Transparency, Accountability and Good Governance</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000723" percentage="3" xml:lang="en"><narrative>Rural Infrastructure and service delivery</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000122" percentage="1" xml:lang="en"><narrative>Monetary and Credit Policies</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000071" percentage="3" xml:lang="en"><narrative>Urban Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000121" percentage="1" xml:lang="en"><narrative>External Finance</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000114" percentage="1" xml:lang="en"><narrative>Tax policy</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000221" percentage="3" xml:lang="en"><narrative>Job Creation</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000043" percentage="34" xml:lang="en"><narrative>Public Administration</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000041" percentage="17" xml:lang="en"><narrative>Public Finance Management</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000012" percentage="3" xml:lang="en"><narrative>Macro-financial policies</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000411" percentage="17" xml:lang="en"><narrative>Public Expenditure Management</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000123" percentage="1" xml:lang="en"><narrative>Macroeconomic Resilience</narrative></sector><collaboration-type code="2" /><default-aid-type code="A02" xml:lang="en"/><default-tied-status code="5" /><budget type="1" status="1">
<period-start iso-date="2010-11-01"/>
<period-end iso-date="2010-11-30"/>
<value currency="USD" value-date="2010-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-12-01"/>
<period-end iso-date="2010-12-31"/>
<value currency="USD" value-date="2010-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-01-01"/>
<period-end iso-date="2011-01-31"/>
<value currency="USD" value-date="2011-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-02-01"/>
<period-end iso-date="2011-02-28"/>
<value currency="USD" value-date="2011-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-03-01"/>
<period-end iso-date="2011-03-31"/>
<value currency="USD" value-date="2011-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-04-01"/>
<period-end iso-date="2011-04-30"/>
<value currency="USD" value-date="2011-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-05-01"/>
<period-end iso-date="2011-05-31"/>
<value currency="USD" value-date="2011-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-06-01"/>
<period-end iso-date="2011-06-30"/>
<value currency="USD" value-date="2011-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-07-01"/>
<period-end iso-date="2011-07-31"/>
<value currency="USD" value-date="2011-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-08-01"/>
<period-end iso-date="2011-08-31"/>
<value currency="USD" value-date="2011-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-09-01"/>
<period-end iso-date="2011-09-30"/>
<value currency="USD" value-date="2011-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-10-01"/>
<period-end iso-date="2011-10-31"/>
<value currency="USD" value-date="2011-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-11-01"/>
<period-end iso-date="2011-11-30"/>
<value currency="USD" value-date="2011-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-12-01"/>
<period-end iso-date="2011-12-31"/>
<value currency="USD" value-date="2011-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-01-01"/>
<period-end iso-date="2012-01-31"/>
<value currency="USD" value-date="2012-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-02-01"/>
<period-end iso-date="2012-02-29"/>
<value currency="USD" value-date="2012-02-29">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-03-01"/>
<period-end iso-date="2012-03-31"/>
<value currency="USD" value-date="2012-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-04-01"/>
<period-end iso-date="2012-04-30"/>
<value currency="USD" value-date="2012-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-05-01"/>
<period-end iso-date="2012-05-31"/>
<value currency="USD" value-date="2012-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-06-01"/>
<period-end iso-date="2012-06-30"/>
<value currency="USD" value-date="2012-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-07-01"/>
<period-end iso-date="2012-07-31"/>
<value currency="USD" value-date="2012-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-08-01"/>
<period-end iso-date="2012-08-31"/>
<value currency="USD" value-date="2012-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2012-09-30"/>
<value currency="USD" value-date="2012-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-10-01"/>
<period-end iso-date="2012-10-31"/>
<value currency="USD" value-date="2012-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-11-01"/>
<period-end iso-date="2012-11-30"/>
<value currency="USD" value-date="2012-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-12-01"/>
<period-end iso-date="2012-12-31"/>
<value currency="USD" value-date="2012-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-01-01"/>
<period-end iso-date="2013-01-31"/>
<value currency="USD" value-date="2013-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-02-01"/>
<period-end iso-date="2013-02-28"/>
<value currency="USD" value-date="2013-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-03-01"/>
<period-end iso-date="2013-03-31"/>
<value currency="USD" value-date="2013-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-04-01"/>
<period-end iso-date="2013-04-30"/>
<value currency="USD" value-date="2013-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-05-01"/>
<period-end iso-date="2013-05-31"/>
<value currency="USD" value-date="2013-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-06-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-07-01"/>
<period-end iso-date="2013-07-31"/>
<value currency="USD" value-date="2013-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-08-01"/>
<period-end iso-date="2013-08-31"/>
<value currency="USD" value-date="2013-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-09-01"/>
<period-end iso-date="2013-09-30"/>
<value currency="USD" value-date="2013-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-10-01"/>
<period-end iso-date="2013-10-31"/>
<value currency="USD" value-date="2013-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-11-01"/>
<period-end iso-date="2013-11-30"/>
<value currency="USD" value-date="2013-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-12-01"/>
<period-end iso-date="2013-12-31"/>
<value currency="USD" value-date="2013-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-01-01"/>
<period-end iso-date="2014-01-31"/>
<value currency="USD" value-date="2014-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-02-01"/>
<period-end iso-date="2014-02-28"/>
<value currency="USD" value-date="2014-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-03-01"/>
<period-end iso-date="2014-03-31"/>
<value currency="USD" value-date="2014-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-04-01"/>
<period-end iso-date="2014-04-30"/>
<value currency="USD" value-date="2014-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-05-01"/>
<period-end iso-date="2014-05-31"/>
<value currency="USD" value-date="2014-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-06-01"/>
<period-end iso-date="2014-06-30"/>
<value currency="USD" value-date="2014-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-07-01"/>
<period-end iso-date="2014-07-31"/>
<value currency="USD" value-date="2014-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-08-01"/>
<period-end iso-date="2014-08-31"/>
<value currency="USD" value-date="2014-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-09-01"/>
<period-end iso-date="2014-09-30"/>
<value currency="USD" value-date="2014-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2014-10-01"/>
<period-end iso-date="2014-10-31"/>
<value currency="USD" value-date="2014-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-11-01"/>
<period-end iso-date="2010-11-30"/>
<value currency="USD" value-date="2010-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-12-01"/>
<period-end iso-date="2010-12-31"/>
<value currency="USD" value-date="2010-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-01-01"/>
<period-end iso-date="2011-01-31"/>
<value currency="USD" value-date="2011-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-02-01"/>
<period-end iso-date="2011-02-28"/>
<value currency="USD" value-date="2011-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-03-01"/>
<period-end iso-date="2011-03-31"/>
<value currency="USD" value-date="2011-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-04-01"/>
<period-end iso-date="2011-04-30"/>
<value currency="USD" value-date="2011-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-05-01"/>
<period-end iso-date="2011-05-31"/>
<value currency="USD" value-date="2011-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-06-01"/>
<period-end iso-date="2011-06-30"/>
<value currency="USD" value-date="2011-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-07-01"/>
<period-end iso-date="2011-07-31"/>
<value currency="USD" value-date="2011-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-08-01"/>
<period-end iso-date="2011-08-31"/>
<value currency="USD" value-date="2011-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-09-01"/>
<period-end iso-date="2011-09-30"/>
<value currency="USD" value-date="2011-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-10-01"/>
<period-end iso-date="2011-10-31"/>
<value currency="USD" value-date="2011-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-11-01"/>
<period-end iso-date="2011-11-30"/>
<value currency="USD" value-date="2011-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-12-01"/>
<period-end iso-date="2011-12-31"/>
<value currency="USD" value-date="2011-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-01-01"/>
<period-end iso-date="2012-01-31"/>
<value currency="USD" value-date="2012-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-02-01"/>
<period-end iso-date="2012-02-29"/>
<value currency="USD" value-date="2012-02-29">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-03-01"/>
<period-end iso-date="2012-03-31"/>
<value currency="USD" value-date="2012-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-04-01"/>
<period-end iso-date="2012-04-30"/>
<value currency="USD" value-date="2012-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-05-01"/>
<period-end iso-date="2012-05-31"/>
<value currency="USD" value-date="2012-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-06-01"/>
<period-end iso-date="2012-06-30"/>
<value currency="USD" value-date="2012-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-07-01"/>
<period-end iso-date="2012-07-31"/>
<value currency="USD" value-date="2012-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-08-01"/>
<period-end iso-date="2012-08-31"/>
<value currency="USD" value-date="2012-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2012-09-30"/>
<value currency="USD" value-date="2012-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-10-01"/>
<period-end iso-date="2012-10-31"/>
<value currency="USD" value-date="2012-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-11-01"/>
<period-end iso-date="2012-11-30"/>
<value currency="USD" value-date="2012-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-12-01"/>
<period-end iso-date="2012-12-31"/>
<value currency="USD" value-date="2012-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-01-01"/>
<period-end iso-date="2013-01-31"/>
<value currency="USD" value-date="2013-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-02-01"/>
<period-end iso-date="2013-02-28"/>
<value currency="USD" value-date="2013-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-03-01"/>
<period-end iso-date="2013-03-31"/>
<value currency="USD" value-date="2013-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-04-01"/>
<period-end iso-date="2013-04-30"/>
<value currency="USD" value-date="2013-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-05-01"/>
<period-end iso-date="2013-05-31"/>
<value currency="USD" value-date="2013-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-06-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-07-01"/>
<period-end iso-date="2013-07-31"/>
<value currency="USD" value-date="2013-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-08-01"/>
<period-end iso-date="2013-08-31"/>
<value currency="USD" value-date="2013-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-09-01"/>
<period-end iso-date="2013-09-30"/>
<value currency="USD" value-date="2013-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-10-01"/>
<period-end iso-date="2013-10-31"/>
<value currency="USD" value-date="2013-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-11-01"/>
<period-end iso-date="2013-11-30"/>
<value currency="USD" value-date="2013-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-12-01"/>
<period-end iso-date="2013-12-31"/>
<value currency="USD" value-date="2013-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-01-01"/>
<period-end iso-date="2014-01-31"/>
<value currency="USD" value-date="2014-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-02-01"/>
<period-end iso-date="2014-02-28"/>
<value currency="USD" value-date="2014-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-03-01"/>
<period-end iso-date="2014-03-31"/>
<value currency="USD" value-date="2014-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-04-01"/>
<period-end iso-date="2014-04-30"/>
<value currency="USD" value-date="2014-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-05-01"/>
<period-end iso-date="2014-05-31"/>
<value currency="USD" value-date="2014-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-06-01"/>
<period-end iso-date="2014-06-30"/>
<value currency="USD" value-date="2014-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-07-01"/>
<period-end iso-date="2014-07-31"/>
<value currency="USD" value-date="2014-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-08-01"/>
<period-end iso-date="2014-08-31"/>
<value currency="USD" value-date="2014-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-09-01"/>
<period-end iso-date="2014-09-30"/>
<value currency="USD" value-date="2014-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2014-10-01"/>
<period-end iso-date="2014-10-31"/>
<value currency="USD" value-date="2014-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">1000000000.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">1000000000.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<capital-spend percentage="0" /><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-procurement/P114154"><title xml:lang="en"><narrative>Contract Awards</narrative></title><category code="A11" /></document-link><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-detail/P114154?lang=en"><title xml:lang="en"><narrative>Project URL</narrative></title><category code="A12" /></document-link><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-procurement/P114154"><title xml:lang="en"><narrative>Procurement Notices</narrative></title><category code="A10" /></document-link><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Real GDP
</narrative></title>
<baseline year="2009" iso-date="2009-04-30" value="-2.60"><comment><narrative>Counterfactual forecast is -2.6, objective for 2009 was not higher than -1.6, actual outcome was -2.2. This indicator was achieved</narrative></comment></baseline>
<period>
<period-start iso-date="2009-04-30" />
<period-end iso-date="1900-01-01"/>
<target value="0.00">

</target>
<actual value="4.70">
<comment><narrative>
Projected.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Budget request gap
</narrative></title>
<baseline year="2008" iso-date="2008-12-31" value="7.00"><comment><narrative>Difference remains below 5 percent in FY2011/12.</narrative></comment></baseline>
<period>
<period-start iso-date="2008-12-31" />
<period-end iso-date="1900-01-01"/>
<target value="2.00">

</target>
<actual value="4.00">
<comment><narrative>
The gap between the MTEF ceilings and agency requests remained below 4 percent.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Government agency Key Performance Indicators
</narrative></title>
<baseline year="2009" iso-date="2009-06-30" value="0.00"><comment><narrative>40 agencies reduced service delivery time, or costs by 5-10 percent in 2009</narrative></comment></baseline>
<period>
<period-start iso-date="2009-06-30" />
<period-end iso-date="1900-01-01"/>
<target value="0.00">

</target>
<actual value="5.00">
<comment><narrative>
Agencies reduced service delivery costs which have been reflected in the doing business report for 2012
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Government Financial Statements certified by Auditor General
</narrative></title>
<baseline year="2009" iso-date="2009-06-01" value="No"><comment><narrative>Auditor General had not certified Government Accounts</narrative></comment></baseline>
<period>
<period-start iso-date="2009-06-01" />
<period-end iso-date="1900-01-01"/>
<target value="">

</target>
<actual value="Yes">

</actual>
</period>
</indicator>
</result></iati-activity><iati-activity xml:lang="en" default-currency="USD" last-updated-datetime="2026-11-20T19:29:57" hierarchy="1"><iati-identifier>44000-P075173</iati-identifier><reporting-org ref="44000" type="40"><narrative  xml:lang="en">World Bank</narrative></reporting-org><title xml:lang="en"><narrative>TH-HIGHWAYS MGMT</narrative></title><description type="2" xml:lang="en"><narrative><![CDATA[]]></narrative></description><description type="1" xml:lang="en"><narrative><![CDATA[]]></narrative></description><participating-org role="1" ref="44001" type="40" xml:lang="en"><narrative>International Bank for Reconstruction and Development</narrative></participating-org><participating-org role="3" ref="44001" type="40" xml:lang="en"><narrative>International Bank for Reconstruction and Development</narrative></participating-org><activity-status code="3" /><activity-date type="1" iso-date="2003-04-17"><narrative>Planned start date of the activity</narrative></activity-date><activity-date type="2" iso-date="2003-12-09"><narrative>Actual start date of the activity</narrative></activity-date><activity-date type="3" iso-date="2013-06-30"><narrative>Planned end date of the activity</narrative></activity-date><activity-date type="4" iso-date="2013-06-30"><narrative>Actual end date of the activity</narrative></activity-date><contact-info type="1"><organisation><narrative>The World Bank</narrative></organisation><person-name><narrative>Chanin Manopiniwes</narrative></person-name><telephone>+1-202-473-1000</telephone><email>chanin@worldbankgroup.org</email><email>pic@worldbank.org</email><mailing-address><narrative>The World Bank, 1818 H Street, NW, Washington, DC 20433 USA</narrative></mailing-address></contact-info>

<recipient-country code="TH" percentage="100"><narrative xml:lang="en">THAILAND</narrative></recipient-country><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001150199" />
            <name><narrative>Amphoe Tha Sala</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>8.6936703 99.885391</pos>
            </point>
            <exactness code="2"/>
            <location-class code="1" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001150200" />
            <name><narrative>Tha Sala</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>8.6673298 99.930779</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001150654" />
            <name><narrative>Amphoe Sichon</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>8.94981 99.813217</pos>
            </point>
            <exactness code="2"/>
            <location-class code="1" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001153783" />
            <name><narrative>Chaiya</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>9.3862495 99.198608</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001155127" />
            <name><narrative>Amphoe Ban Pong</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>13.8166 99.821472</pos>
            </point>
            <exactness code="2"/>
            <location-class code="1" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001615831" />
            <name><narrative>Ban Nong Bua Khok</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>15.41933 101.82767</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0007510858" />
            <name><narrative>Amphoe Nikhom Kham Soi</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>16.35375 104.55864</pos>
            </point>
            <exactness code="2"/>
            <location-class code="1" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0007602008" />
            <name><narrative>Sichon</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>9.0107203 99.900658</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001609068" />
            <name><narrative>Loeng Nok Tha</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>16.2075 104.55528</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001609067" />
            <name><narrative>Amphoe Loeng Nok Tha</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>16.20433 104.51442</pos>
            </point>
            <exactness code="2"/>
            <location-class code="1" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001605239" />
            <name><narrative>Udon Thani</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>17.41567 102.78589</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><location>
            <location-reach code="1" />
            <location-id vocabulary="G1" code="0001608382" />
            <name><narrative>Nikhom Kham Soi</narrative></name>
            <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
            <pos>16.37167 104.55147</pos>
            </point>
            <exactness code="2"/>
            <location-class code="2" />
        </location><sector vocabulary="1" code="21012" percentage="7" xml:lang="en"/><sector vocabulary="1" code="21023" percentage="93" xml:lang="en"/><sector vocabulary="99" vocabulary-uri="http://pubdocs.worldbank.org/en/538321490128452070/Sector-Taxonomy-and-definitions.pdf" code="TI" percentage="95.0000000" xml:lang="en"><narrative>FY17 - Rural and Inter-Urban Roads</narrative></sector><sector vocabulary="99" vocabulary-uri="http://pubdocs.worldbank.org/en/538321490128452070/Sector-Taxonomy-and-definitions.pdf" code="BH" percentage="5.00000000" xml:lang="en"><narrative>FY17 - Sub-National Government</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000032" percentage="7" xml:lang="en"><narrative>Financial Infrastructure and Access</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000032" percentage="7" xml:lang="en"><narrative>Financial Infrastructure and Access</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000024" percentage="7" xml:lang="en"><narrative>Enterprise Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000072" percentage="8" xml:lang="en"><narrative>Rural Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000723" percentage="8" xml:lang="en"><narrative>Rural Infrastructure and service delivery</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000071" percentage="8" xml:lang="en"><narrative>Urban Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000072" percentage="8" xml:lang="en"><narrative>Rural Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000221" percentage="8" xml:lang="en"><narrative>Job Creation</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000023" percentage="10" xml:lang="en"><narrative>Public Private Partnerships</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000022" percentage="8" xml:lang="en"><narrative>Jobs</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000062" percentage="24" xml:lang="en"><narrative>Disease Control</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000243" percentage="7" xml:lang="en"><narrative>MSME Development</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000711" percentage="8" xml:lang="en"><narrative>Urban Infrastructure and Service Delivery</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000711" percentage="8" xml:lang="en"><narrative>Urban Infrastructure and Service Delivery</narrative></sector><sector vocabulary="98" vocabulary-uri="http://pubdocs.worldbank.org/en/275841490966525495/Theme-Taxonomy-and-definitions.pdf" code="000323" percentage="7" xml:lang="en"><narrative>MSME Finance</narrative></sector><collaboration-type code="2" /><default-aid-type code="C01" xml:lang="en"/><default-tied-status code="5" /><budget type="1" status="1">
<period-start iso-date="2003-12-01"/>
<period-end iso-date="2003-12-31"/>
<value currency="USD" value-date="2003-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-01-01"/>
<period-end iso-date="2004-01-31"/>
<value currency="USD" value-date="2004-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-02-01"/>
<period-end iso-date="2004-02-29"/>
<value currency="USD" value-date="2004-02-29">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-03-01"/>
<period-end iso-date="2004-03-31"/>
<value currency="USD" value-date="2004-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-04-01"/>
<period-end iso-date="2004-04-30"/>
<value currency="USD" value-date="2004-04-30">1666666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-05-01"/>
<period-end iso-date="2004-05-31"/>
<value currency="USD" value-date="2004-05-31">1666666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-06-01"/>
<period-end iso-date="2004-06-30"/>
<value currency="USD" value-date="2004-06-30">1666666.66</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-07-01"/>
<period-end iso-date="2004-07-31"/>
<value currency="USD" value-date="2004-07-31">1666666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-08-01"/>
<period-end iso-date="2004-08-31"/>
<value currency="USD" value-date="2004-08-31">1666666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-09-01"/>
<period-end iso-date="2004-09-30"/>
<value currency="USD" value-date="2004-09-30">1666666.66</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-10-01"/>
<period-end iso-date="2004-10-31"/>
<value currency="USD" value-date="2004-10-31">2166666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-11-01"/>
<period-end iso-date="2004-11-30"/>
<value currency="USD" value-date="2004-11-30">2166666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2004-12-01"/>
<period-end iso-date="2004-12-31"/>
<value currency="USD" value-date="2004-12-31">2166666.66</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-01-01"/>
<period-end iso-date="2005-01-31"/>
<value currency="USD" value-date="2005-01-31">2333333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-02-01"/>
<period-end iso-date="2005-02-28"/>
<value currency="USD" value-date="2005-02-28">2333333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-03-01"/>
<period-end iso-date="2005-03-31"/>
<value currency="USD" value-date="2005-03-31">2333333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-04-01"/>
<period-end iso-date="2005-04-30"/>
<value currency="USD" value-date="2005-04-30">2433333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-05-01"/>
<period-end iso-date="2005-05-31"/>
<value currency="USD" value-date="2005-05-31">2433333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-06-01"/>
<period-end iso-date="2005-06-30"/>
<value currency="USD" value-date="2005-06-30">2433333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-07-01"/>
<period-end iso-date="2005-07-31"/>
<value currency="USD" value-date="2005-07-31">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-08-01"/>
<period-end iso-date="2005-08-31"/>
<value currency="USD" value-date="2005-08-31">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-09-01"/>
<period-end iso-date="2005-09-30"/>
<value currency="USD" value-date="2005-09-30">2208333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-10-01"/>
<period-end iso-date="2005-10-31"/>
<value currency="USD" value-date="2005-10-31">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-11-01"/>
<period-end iso-date="2005-11-30"/>
<value currency="USD" value-date="2005-11-30">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2005-12-01"/>
<period-end iso-date="2005-12-31"/>
<value currency="USD" value-date="2005-12-31">2208333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-01-01"/>
<period-end iso-date="2006-01-31"/>
<value currency="USD" value-date="2006-01-31">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-02-01"/>
<period-end iso-date="2006-02-28"/>
<value currency="USD" value-date="2006-02-28">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-03-01"/>
<period-end iso-date="2006-03-31"/>
<value currency="USD" value-date="2006-03-31">2208333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-04-01"/>
<period-end iso-date="2006-04-30"/>
<value currency="USD" value-date="2006-04-30">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-05-01"/>
<period-end iso-date="2006-05-31"/>
<value currency="USD" value-date="2006-05-31">2208333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-06-01"/>
<period-end iso-date="2006-06-30"/>
<value currency="USD" value-date="2006-06-30">2208333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-07-01"/>
<period-end iso-date="2006-07-31"/>
<value currency="USD" value-date="2006-07-31">1500000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-08-01"/>
<period-end iso-date="2006-08-31"/>
<value currency="USD" value-date="2006-08-31">1500000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-09-01"/>
<period-end iso-date="2006-09-30"/>
<value currency="USD" value-date="2006-09-30">1500000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-10-01"/>
<period-end iso-date="2006-10-31"/>
<value currency="USD" value-date="2006-10-31">1458333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-11-01"/>
<period-end iso-date="2006-11-30"/>
<value currency="USD" value-date="2006-11-30">1458333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2006-12-01"/>
<period-end iso-date="2006-12-31"/>
<value currency="USD" value-date="2006-12-31">1458333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-01-01"/>
<period-end iso-date="2007-01-31"/>
<value currency="USD" value-date="2007-01-31">1458333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-02-01"/>
<period-end iso-date="2007-02-28"/>
<value currency="USD" value-date="2007-02-28">1458333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-03-01"/>
<period-end iso-date="2007-03-31"/>
<value currency="USD" value-date="2007-03-31">1458333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-04-01"/>
<period-end iso-date="2007-04-30"/>
<value currency="USD" value-date="2007-04-30">1413333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-05-01"/>
<period-end iso-date="2007-05-31"/>
<value currency="USD" value-date="2007-05-31">1413333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-06-01"/>
<period-end iso-date="2007-06-30"/>
<value currency="USD" value-date="2007-06-30">1413333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-07-01"/>
<period-end iso-date="2007-07-31"/>
<value currency="USD" value-date="2007-07-31">1333333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-08-01"/>
<period-end iso-date="2007-08-31"/>
<value currency="USD" value-date="2007-08-31">1333333.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-09-01"/>
<period-end iso-date="2007-09-30"/>
<value currency="USD" value-date="2007-09-30">1333333.34</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-10-01"/>
<period-end iso-date="2007-10-31"/>
<value currency="USD" value-date="2007-10-31">1000000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-11-01"/>
<period-end iso-date="2007-11-30"/>
<value currency="USD" value-date="2007-11-30">1000000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2007-12-01"/>
<period-end iso-date="2007-12-31"/>
<value currency="USD" value-date="2007-12-31">1000000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-01-01"/>
<period-end iso-date="2008-01-31"/>
<value currency="USD" value-date="2008-01-31">666666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-02-01"/>
<period-end iso-date="2008-02-29"/>
<value currency="USD" value-date="2008-02-29">666666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-03-01"/>
<period-end iso-date="2008-03-31"/>
<value currency="USD" value-date="2008-03-31">666666.66</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-04-01"/>
<period-end iso-date="2008-04-30"/>
<value currency="USD" value-date="2008-04-30">166666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-05-01"/>
<period-end iso-date="2008-05-31"/>
<value currency="USD" value-date="2008-05-31">166666.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-06-01"/>
<period-end iso-date="2008-06-30"/>
<value currency="USD" value-date="2008-06-30">166666.66</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-07-01"/>
<period-end iso-date="2008-07-31"/>
<value currency="USD" value-date="2008-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-08-01"/>
<period-end iso-date="2008-08-31"/>
<value currency="USD" value-date="2008-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-09-01"/>
<period-end iso-date="2008-09-30"/>
<value currency="USD" value-date="2008-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-10-01"/>
<period-end iso-date="2008-10-31"/>
<value currency="USD" value-date="2008-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-11-01"/>
<period-end iso-date="2008-11-30"/>
<value currency="USD" value-date="2008-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2008-12-01"/>
<period-end iso-date="2008-12-31"/>
<value currency="USD" value-date="2008-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-01-01"/>
<period-end iso-date="2009-01-31"/>
<value currency="USD" value-date="2009-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-02-01"/>
<period-end iso-date="2009-02-28"/>
<value currency="USD" value-date="2009-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-03-01"/>
<period-end iso-date="2009-03-31"/>
<value currency="USD" value-date="2009-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-04-01"/>
<period-end iso-date="2009-04-30"/>
<value currency="USD" value-date="2009-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-05-01"/>
<period-end iso-date="2009-05-31"/>
<value currency="USD" value-date="2009-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-06-01"/>
<period-end iso-date="2009-06-30"/>
<value currency="USD" value-date="2009-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-07-01"/>
<period-end iso-date="2009-07-31"/>
<value currency="USD" value-date="2009-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-08-01"/>
<period-end iso-date="2009-08-31"/>
<value currency="USD" value-date="2009-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-09-01"/>
<period-end iso-date="2009-09-30"/>
<value currency="USD" value-date="2009-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-10-01"/>
<period-end iso-date="2009-10-31"/>
<value currency="USD" value-date="2009-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-11-01"/>
<period-end iso-date="2009-11-30"/>
<value currency="USD" value-date="2009-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2009-12-01"/>
<period-end iso-date="2009-12-31"/>
<value currency="USD" value-date="2009-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-01-01"/>
<period-end iso-date="2010-01-31"/>
<value currency="USD" value-date="2010-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-02-01"/>
<period-end iso-date="2010-02-28"/>
<value currency="USD" value-date="2010-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-03-01"/>
<period-end iso-date="2010-03-31"/>
<value currency="USD" value-date="2010-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-04-01"/>
<period-end iso-date="2010-04-30"/>
<value currency="USD" value-date="2010-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-05-01"/>
<period-end iso-date="2010-05-31"/>
<value currency="USD" value-date="2010-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-06-01"/>
<period-end iso-date="2010-06-30"/>
<value currency="USD" value-date="2010-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-07-01"/>
<period-end iso-date="2010-07-31"/>
<value currency="USD" value-date="2010-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-08-01"/>
<period-end iso-date="2010-08-31"/>
<value currency="USD" value-date="2010-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-09-01"/>
<period-end iso-date="2010-09-30"/>
<value currency="USD" value-date="2010-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-10-01"/>
<period-end iso-date="2010-10-31"/>
<value currency="USD" value-date="2010-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-11-01"/>
<period-end iso-date="2010-11-30"/>
<value currency="USD" value-date="2010-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2010-12-01"/>
<period-end iso-date="2010-12-31"/>
<value currency="USD" value-date="2010-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-01-01"/>
<period-end iso-date="2011-01-31"/>
<value currency="USD" value-date="2011-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-02-01"/>
<period-end iso-date="2011-02-28"/>
<value currency="USD" value-date="2011-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-03-01"/>
<period-end iso-date="2011-03-31"/>
<value currency="USD" value-date="2011-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-04-01"/>
<period-end iso-date="2011-04-30"/>
<value currency="USD" value-date="2011-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-05-01"/>
<period-end iso-date="2011-05-31"/>
<value currency="USD" value-date="2011-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-06-01"/>
<period-end iso-date="2011-06-30"/>
<value currency="USD" value-date="2011-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-07-01"/>
<period-end iso-date="2011-07-31"/>
<value currency="USD" value-date="2011-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-08-01"/>
<period-end iso-date="2011-08-31"/>
<value currency="USD" value-date="2011-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-09-01"/>
<period-end iso-date="2011-09-30"/>
<value currency="USD" value-date="2011-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-10-01"/>
<period-end iso-date="2011-10-31"/>
<value currency="USD" value-date="2011-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-11-01"/>
<period-end iso-date="2011-11-30"/>
<value currency="USD" value-date="2011-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2011-12-01"/>
<period-end iso-date="2011-12-31"/>
<value currency="USD" value-date="2011-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-01-01"/>
<period-end iso-date="2012-01-31"/>
<value currency="USD" value-date="2012-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-02-01"/>
<period-end iso-date="2012-02-29"/>
<value currency="USD" value-date="2012-02-29">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-03-01"/>
<period-end iso-date="2012-03-31"/>
<value currency="USD" value-date="2012-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-04-01"/>
<period-end iso-date="2012-04-30"/>
<value currency="USD" value-date="2012-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-05-01"/>
<period-end iso-date="2012-05-31"/>
<value currency="USD" value-date="2012-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-06-01"/>
<period-end iso-date="2012-06-30"/>
<value currency="USD" value-date="2012-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-07-01"/>
<period-end iso-date="2012-07-31"/>
<value currency="USD" value-date="2012-07-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-08-01"/>
<period-end iso-date="2012-08-31"/>
<value currency="USD" value-date="2012-08-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2012-09-30"/>
<value currency="USD" value-date="2012-09-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-10-01"/>
<period-end iso-date="2012-10-31"/>
<value currency="USD" value-date="2012-10-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-11-01"/>
<period-end iso-date="2012-11-30"/>
<value currency="USD" value-date="2012-11-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2012-12-01"/>
<period-end iso-date="2012-12-31"/>
<value currency="USD" value-date="2012-12-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-01-01"/>
<period-end iso-date="2013-01-31"/>
<value currency="USD" value-date="2013-01-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-02-01"/>
<period-end iso-date="2013-02-28"/>
<value currency="USD" value-date="2013-02-28">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-03-01"/>
<period-end iso-date="2013-03-31"/>
<value currency="USD" value-date="2013-03-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-04-01"/>
<period-end iso-date="2013-04-30"/>
<value currency="USD" value-date="2013-04-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-05-01"/>
<period-end iso-date="2013-05-31"/>
<value currency="USD" value-date="2013-05-31">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-06-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2003-12-01"/>
<period-end iso-date="2003-12-31"/>
<value currency="USD" value-date="2003-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-01-01"/>
<period-end iso-date="2004-01-31"/>
<value currency="USD" value-date="2004-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-02-01"/>
<period-end iso-date="2004-02-29"/>
<value currency="USD" value-date="2004-02-29">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-03-01"/>
<period-end iso-date="2004-03-31"/>
<value currency="USD" value-date="2004-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-04-01"/>
<period-end iso-date="2004-04-30"/>
<value currency="USD" value-date="2004-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-05-01"/>
<period-end iso-date="2004-05-31"/>
<value currency="USD" value-date="2004-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-06-01"/>
<period-end iso-date="2004-06-30"/>
<value currency="USD" value-date="2004-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-07-01"/>
<period-end iso-date="2004-07-31"/>
<value currency="USD" value-date="2004-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-08-01"/>
<period-end iso-date="2004-08-31"/>
<value currency="USD" value-date="2004-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-09-01"/>
<period-end iso-date="2004-09-30"/>
<value currency="USD" value-date="2004-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-10-01"/>
<period-end iso-date="2004-10-31"/>
<value currency="USD" value-date="2004-10-31">2166666.67</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-11-01"/>
<period-end iso-date="2004-11-30"/>
<value currency="USD" value-date="2004-11-30">2166666.67</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2004-12-01"/>
<period-end iso-date="2004-12-31"/>
<value currency="USD" value-date="2004-12-31">2166666.66</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-01-01"/>
<period-end iso-date="2005-01-31"/>
<value currency="USD" value-date="2005-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-02-01"/>
<period-end iso-date="2005-02-28"/>
<value currency="USD" value-date="2005-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-03-01"/>
<period-end iso-date="2005-03-31"/>
<value currency="USD" value-date="2005-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-04-01"/>
<period-end iso-date="2005-04-30"/>
<value currency="USD" value-date="2005-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-05-01"/>
<period-end iso-date="2005-05-31"/>
<value currency="USD" value-date="2005-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-06-01"/>
<period-end iso-date="2005-06-30"/>
<value currency="USD" value-date="2005-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-07-01"/>
<period-end iso-date="2005-07-31"/>
<value currency="USD" value-date="2005-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-08-01"/>
<period-end iso-date="2005-08-31"/>
<value currency="USD" value-date="2005-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-09-01"/>
<period-end iso-date="2005-09-30"/>
<value currency="USD" value-date="2005-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-10-01"/>
<period-end iso-date="2005-10-31"/>
<value currency="USD" value-date="2005-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-11-01"/>
<period-end iso-date="2005-11-30"/>
<value currency="USD" value-date="2005-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2005-12-01"/>
<period-end iso-date="2005-12-31"/>
<value currency="USD" value-date="2005-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-01-01"/>
<period-end iso-date="2006-01-31"/>
<value currency="USD" value-date="2006-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-02-01"/>
<period-end iso-date="2006-02-28"/>
<value currency="USD" value-date="2006-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-03-01"/>
<period-end iso-date="2006-03-31"/>
<value currency="USD" value-date="2006-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-04-01"/>
<period-end iso-date="2006-04-30"/>
<value currency="USD" value-date="2006-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-05-01"/>
<period-end iso-date="2006-05-31"/>
<value currency="USD" value-date="2006-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-06-01"/>
<period-end iso-date="2006-06-30"/>
<value currency="USD" value-date="2006-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-07-01"/>
<period-end iso-date="2006-07-31"/>
<value currency="USD" value-date="2006-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-08-01"/>
<period-end iso-date="2006-08-31"/>
<value currency="USD" value-date="2006-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-09-01"/>
<period-end iso-date="2006-09-30"/>
<value currency="USD" value-date="2006-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-10-01"/>
<period-end iso-date="2006-10-31"/>
<value currency="USD" value-date="2006-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-11-01"/>
<period-end iso-date="2006-11-30"/>
<value currency="USD" value-date="2006-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2006-12-01"/>
<period-end iso-date="2006-12-31"/>
<value currency="USD" value-date="2006-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-01-01"/>
<period-end iso-date="2007-01-31"/>
<value currency="USD" value-date="2007-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-02-01"/>
<period-end iso-date="2007-02-28"/>
<value currency="USD" value-date="2007-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-03-01"/>
<period-end iso-date="2007-03-31"/>
<value currency="USD" value-date="2007-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-04-01"/>
<period-end iso-date="2007-04-30"/>
<value currency="USD" value-date="2007-04-30">1413333.33</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-05-01"/>
<period-end iso-date="2007-05-31"/>
<value currency="USD" value-date="2007-05-31">1413333.33</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-06-01"/>
<period-end iso-date="2007-06-30"/>
<value currency="USD" value-date="2007-06-30">1413333.34</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-07-01"/>
<period-end iso-date="2007-07-31"/>
<value currency="USD" value-date="2007-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-08-01"/>
<period-end iso-date="2007-08-31"/>
<value currency="USD" value-date="2007-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-09-01"/>
<period-end iso-date="2007-09-30"/>
<value currency="USD" value-date="2007-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-10-01"/>
<period-end iso-date="2007-10-31"/>
<value currency="USD" value-date="2007-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-11-01"/>
<period-end iso-date="2007-11-30"/>
<value currency="USD" value-date="2007-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2007-12-01"/>
<period-end iso-date="2007-12-31"/>
<value currency="USD" value-date="2007-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-01-01"/>
<period-end iso-date="2008-01-31"/>
<value currency="USD" value-date="2008-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-02-01"/>
<period-end iso-date="2008-02-29"/>
<value currency="USD" value-date="2008-02-29">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-03-01"/>
<period-end iso-date="2008-03-31"/>
<value currency="USD" value-date="2008-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-04-01"/>
<period-end iso-date="2008-04-30"/>
<value currency="USD" value-date="2008-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-05-01"/>
<period-end iso-date="2008-05-31"/>
<value currency="USD" value-date="2008-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-06-01"/>
<period-end iso-date="2008-06-30"/>
<value currency="USD" value-date="2008-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-07-01"/>
<period-end iso-date="2008-07-31"/>
<value currency="USD" value-date="2008-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-08-01"/>
<period-end iso-date="2008-08-31"/>
<value currency="USD" value-date="2008-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-09-01"/>
<period-end iso-date="2008-09-30"/>
<value currency="USD" value-date="2008-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-10-01"/>
<period-end iso-date="2008-10-31"/>
<value currency="USD" value-date="2008-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-11-01"/>
<period-end iso-date="2008-11-30"/>
<value currency="USD" value-date="2008-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2008-12-01"/>
<period-end iso-date="2008-12-31"/>
<value currency="USD" value-date="2008-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-01-01"/>
<period-end iso-date="2009-01-31"/>
<value currency="USD" value-date="2009-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-02-01"/>
<period-end iso-date="2009-02-28"/>
<value currency="USD" value-date="2009-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-03-01"/>
<period-end iso-date="2009-03-31"/>
<value currency="USD" value-date="2009-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-04-01"/>
<period-end iso-date="2009-04-30"/>
<value currency="USD" value-date="2009-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-05-01"/>
<period-end iso-date="2009-05-31"/>
<value currency="USD" value-date="2009-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-06-01"/>
<period-end iso-date="2009-06-30"/>
<value currency="USD" value-date="2009-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-07-01"/>
<period-end iso-date="2009-07-31"/>
<value currency="USD" value-date="2009-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-08-01"/>
<period-end iso-date="2009-08-31"/>
<value currency="USD" value-date="2009-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-09-01"/>
<period-end iso-date="2009-09-30"/>
<value currency="USD" value-date="2009-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-10-01"/>
<period-end iso-date="2009-10-31"/>
<value currency="USD" value-date="2009-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-11-01"/>
<period-end iso-date="2009-11-30"/>
<value currency="USD" value-date="2009-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2009-12-01"/>
<period-end iso-date="2009-12-31"/>
<value currency="USD" value-date="2009-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-01-01"/>
<period-end iso-date="2010-01-31"/>
<value currency="USD" value-date="2010-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-02-01"/>
<period-end iso-date="2010-02-28"/>
<value currency="USD" value-date="2010-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-03-01"/>
<period-end iso-date="2010-03-31"/>
<value currency="USD" value-date="2010-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-04-01"/>
<period-end iso-date="2010-04-30"/>
<value currency="USD" value-date="2010-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-05-01"/>
<period-end iso-date="2010-05-31"/>
<value currency="USD" value-date="2010-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-06-01"/>
<period-end iso-date="2010-06-30"/>
<value currency="USD" value-date="2010-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-07-01"/>
<period-end iso-date="2010-07-31"/>
<value currency="USD" value-date="2010-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-08-01"/>
<period-end iso-date="2010-08-31"/>
<value currency="USD" value-date="2010-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-09-01"/>
<period-end iso-date="2010-09-30"/>
<value currency="USD" value-date="2010-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-10-01"/>
<period-end iso-date="2010-10-31"/>
<value currency="USD" value-date="2010-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-11-01"/>
<period-end iso-date="2010-11-30"/>
<value currency="USD" value-date="2010-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2010-12-01"/>
<period-end iso-date="2010-12-31"/>
<value currency="USD" value-date="2010-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-01-01"/>
<period-end iso-date="2011-01-31"/>
<value currency="USD" value-date="2011-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-02-01"/>
<period-end iso-date="2011-02-28"/>
<value currency="USD" value-date="2011-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-03-01"/>
<period-end iso-date="2011-03-31"/>
<value currency="USD" value-date="2011-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-04-01"/>
<period-end iso-date="2011-04-30"/>
<value currency="USD" value-date="2011-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-05-01"/>
<period-end iso-date="2011-05-31"/>
<value currency="USD" value-date="2011-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-06-01"/>
<period-end iso-date="2011-06-30"/>
<value currency="USD" value-date="2011-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-07-01"/>
<period-end iso-date="2011-07-31"/>
<value currency="USD" value-date="2011-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-08-01"/>
<period-end iso-date="2011-08-31"/>
<value currency="USD" value-date="2011-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-09-01"/>
<period-end iso-date="2011-09-30"/>
<value currency="USD" value-date="2011-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-10-01"/>
<period-end iso-date="2011-10-31"/>
<value currency="USD" value-date="2011-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-11-01"/>
<period-end iso-date="2011-11-30"/>
<value currency="USD" value-date="2011-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2011-12-01"/>
<period-end iso-date="2011-12-31"/>
<value currency="USD" value-date="2011-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-01-01"/>
<period-end iso-date="2012-01-31"/>
<value currency="USD" value-date="2012-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-02-01"/>
<period-end iso-date="2012-02-29"/>
<value currency="USD" value-date="2012-02-29">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-03-01"/>
<period-end iso-date="2012-03-31"/>
<value currency="USD" value-date="2012-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-04-01"/>
<period-end iso-date="2012-04-30"/>
<value currency="USD" value-date="2012-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-05-01"/>
<period-end iso-date="2012-05-31"/>
<value currency="USD" value-date="2012-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-06-01"/>
<period-end iso-date="2012-06-30"/>
<value currency="USD" value-date="2012-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-07-01"/>
<period-end iso-date="2012-07-31"/>
<value currency="USD" value-date="2012-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-08-01"/>
<period-end iso-date="2012-08-31"/>
<value currency="USD" value-date="2012-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-09-01"/>
<period-end iso-date="2012-09-30"/>
<value currency="USD" value-date="2012-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-10-01"/>
<period-end iso-date="2012-10-31"/>
<value currency="USD" value-date="2012-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-11-01"/>
<period-end iso-date="2012-11-30"/>
<value currency="USD" value-date="2012-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2012-12-01"/>
<period-end iso-date="2012-12-31"/>
<value currency="USD" value-date="2012-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-01-01"/>
<period-end iso-date="2013-01-31"/>
<value currency="USD" value-date="2013-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-02-01"/>
<period-end iso-date="2013-02-28"/>
<value currency="USD" value-date="2013-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-03-01"/>
<period-end iso-date="2013-03-31"/>
<value currency="USD" value-date="2013-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-04-01"/>
<period-end iso-date="2013-04-30"/>
<value currency="USD" value-date="2013-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-05-01"/>
<period-end iso-date="2013-05-31"/>
<value currency="USD" value-date="2013-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-06-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2013-06-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2013-06-01"/>
<period-end iso-date="2013-06-30"/>
<value currency="USD" value-date="2013-06-30">0.00</value>
</budget>
<capital-spend percentage="100" /><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-procurement/P075173"><title xml:lang="en"><narrative>Contract Awards</narrative></title><category code="A11" /></document-link><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-detail/P075173?lang=en"><title xml:lang="en"><narrative>Project URL</narrative></title><category code="A12" /></document-link><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-procurement/P075173"><title xml:lang="en"><narrative>Procurement Notices</narrative></title><category code="A10" /></document-link><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Reduced average unit cost/km of maintenance in real terms
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="403"><comment><narrative>on the baseline of 403 Baht/M2</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="362.7">
<comment><narrative>
362.7 Baht/m2 = Baseline - 10%
</narrative></comment>
</target>
<actual value="378.80">
<comment><narrative>
Not updated as no more maintenance works have been implemented since last update.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Periodic maintenance of 960 km of project roads completed using conventional contracting methods with SMEs
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="960 Km">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="1,556 km">
<comment><narrative>
Achieved using conventional methods with SMEs
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Road safety awareness campaigns carried out
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Campaigns carried out">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="Campaigns carried out">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
PPP financing for the proposed Bang Pa-in to Nakhon Ratchasima Motorway reached bidding stage
</narrative></title>
<baseline year="2010" iso-date="2010-05-21" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2010-05-21" />
<period-end iso-date="2013-06-30" />
<target value="No">
<comment><narrative>
Not achieved
</narrative></comment>
</target>
<actual value="No">
<comment><narrative>
Procurement process canceled due to loan cancellation.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Framework and case study for PPP in highways developed and results adopted by DOH
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Framework and study adopted">

</target>
<actual value="Framework and study adopted">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Asset value of road network increased by 0.2% by EOP       (or decline reversed)
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="323.60"><comment><narrative>291.28 million Baht/km for maintenance project sections + 32.32 million Baht/ km for 3 widening projects</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="324.25">
<comment><narrative>
Achieved under original loan (324.25 Baht/km = Baseline + 0.2%)
</narrative></comment>
</target>
<actual value="331.62">
<comment><narrative>
Not updated as it was achieved under original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Three overpasses constructed at critical locations as per specifications
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="3">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="3">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Road user costs reduced by at least 10% on target roads under additional financing
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="5.72">
<comment><narrative>
Not achieved under the additional financing loan (5.715 Baht/km = Baseline - 10%)
</narrative></comment>
</target>
<actual value="6.35">
<comment><narrative>
Not updated as the additional financing loan is canceled.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
National road database established, updated annually, and used for planning, programming, budgeting, and monitoring of highway investments and maintenance expenditure
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="No database"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="Established and functional">

</target>
<actual value="Database established and functional.">
<comment><narrative>
DOH is improving the database.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Accident Research Center established at AIT in collaboration with GRSP
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Center established">

</target>
<actual value="Thailand Accident Research Center established">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
PPP financing for the proposed Bang Pa-in to Nakhon Ratchasima Motorway reached bidding stage
</narrative></title>
<baseline year="2010" iso-date="2010-05-21" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2010-05-21" />
<period-end iso-date="2013-06-30" />
<target value="Yes">

</target>
<actual value="No">
<comment><narrative>
Consultancy is in procurement process.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Road safety awareness campaigns carried out
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Campaigns carried out">

</target>
<actual value="Campaigns carried out">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Additional 216 km of priority national highways widened for four lanes as per specification
</narrative></title>
<baseline year="2010" iso-date="2010-05-21" value="0.00"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2010-05-21" />
<period-end iso-date="2013-06-30" />
<target value="216.00">

</target>
<actual value="0.00">
<comment><narrative>
Civil Works not yet started, and now at bid document preparation stage
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Reduce vehicle operating costs by 10-15% on target roads
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="4.68"><comment><narrative>4.68 Baht per vehicle-km</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="3.978-4.212">
<comment><narrative>
3.978-4.212 Baht/v-km represent 10-15% reduction from baseline
</narrative></comment>
</target>
<actual value="4.53">
<comment><narrative>
Based on target roads for the case study with control factors
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Annual report covering DOH#s environmental performance disseminated to the public
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Reports disseminated">

</target>
<actual value="Reports disseminated">
<comment><narrative>
Achieved under original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Average roughness of target roads less than 3.5 IRI.
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="4.43"><comment><narrative>IRI</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="less than 3.5 IRI">
<comment><narrative>
Achieved for targeted roads
</narrative></comment>
</target>
<actual value="2.24">
<comment><narrative>
Not updated.  All maintenance works completed as per specification.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Pilot long-term performance-based management and maintenance contract designed for
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="No design."><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="Design completed">
<comment><narrative>
Substantially achieved
</narrative></comment>
</target>
<actual value="Design work substantially completed and will be completed by June 30, 2013">
<comment><narrative>
To be completed by June 30, 2013
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Average travel time reduced on widened sections by 20-30%
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Total of 52.2-59.6 minutes of travel time on three widening sections (20-30% reduction)">

</target>
<actual value="Total of 53.60 minutes (avg 96.57 km/hr)">
<comment><narrative>
Achieved for the completed sections with original loan.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Road user costs reduced by at least 10% on target roads under additional financing
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="5.72">
<comment><narrative>
5.715 Baht/km = Baseline - 10%
</narrative></comment>
</target>
<actual value="6.35">
<comment><narrative>
Not updated as procurement of works for target roads is underway.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Reduced average unit cost/km of maintenance in real terms
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="403"><comment><narrative>on the baseline of 403 Baht/M2</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="362.7">
<comment><narrative>
Achieved (362.7 Baht/m2 = Baseline - 10%)
</narrative></comment>
</target>
<actual value="325.6">
<comment><narrative>
117km of additional maintenance in late 2011
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
66 hazardous locations improved as per specifications
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="66">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="Over 100">
<comment><narrative>
Similar works are taken by DOH as routine.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Average roughness of target roads less than 3.5 IRI.
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="4.43"><comment><narrative>IRI</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="less than 3.5 IRI">

</target>
<actual value="2.24">
<comment><narrative>
Not updated.  All maintenance works completed as per specification.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Framework and case study for PPP in highways developed and results adopted by DOH
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Framework and study adopted">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="Study completed, and framework being followed by DOH for projects not funded by the Bank.">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Average delays reduced at improved intersections by 60%
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="30.47 seconds average delay in three improved locations (60% reduction)">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="27.08 seconds average delay in three improved locations">
<comment><narrative>
No update as the works were completed.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Roads rehabilitated, Non-rural
</narrative></title>
<baseline year="2004" iso-date="2004-03-03" value="0.00"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-03" />
<period-end iso-date="2013-06-30" />
<target value="960.00">

</target>
<actual value="1556.00">
<comment><narrative>
Achieved using conventional methods with SMEs
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Pilot long-term performance-based management and maintenance contract designed for
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="No design."><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="Design completed">

</target>
<actual value="Consultancy under procurement">
<comment><narrative>
Consultancy under procurement
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Periodic maintenance of 960 km of project roads completed using conventional contracting methods with SMEs
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="960 Km">

</target>
<actual value="1,556 km">
<comment><narrative>
Achieved using conventional methods with SMEs
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Annual report covering DOH#s environmental performance disseminated to the public
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Reports disseminated">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="Reports disseminated">
<comment><narrative>
Achieved under original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Modern centralized database, road maintenance management system and bridge management system implemented and operational
</narrative></title>
<baseline year="2004" iso-date="2004-04-30" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-04-30" />
<period-end iso-date="2013-06-30" />
<target value="System operational">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="Systems are operational.">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Additional 216 km of priority national highways widened for four lanes as per specification
</narrative></title>
<baseline year="2010" iso-date="2010-05-21" value="0.00"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2010-05-21" />
<period-end iso-date="2013-06-30" />
<target value="216.00">
<comment><narrative>
Not achieved
</narrative></comment>
</target>
<actual value="0.00">
<comment><narrative>
Civil Works not started prior to loan cancellation.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Accident Research Center established at AIT in collaboration with GRSP
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Center established">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="Center established and well regarded in Thailand">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
National road database established, updated annually, and used for planning, programming, budgeting, and monitoring of highway investments and maintenance expenditure
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="No database"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="Established and functional">
<comment><narrative>
Achieved under original loan
</narrative></comment>
</target>
<actual value="Database functional">
<comment><narrative>
DOH continues to improve the database.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
73 km of priority national highways widened to four lanes as per specifications
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="0 km"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2009-06-30" />
<target value="73 km">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="86.27 km">
<comment><narrative>
Achieved.  The actual length was longer than length at Appraisal due to addition of a bypass.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
73 km of priority national highways widened to four lanes as per specifications
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="0 km"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2009-06-30" />
<target value="73 km">

</target>
<actual value="86.27 km">
<comment><narrative>
Achieved.  The actual length was longer than length at Appraisal due to addition of a bypass.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Reduce vehicle operating costs by 10-15% on target roads
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="4.68"><comment><narrative>4.68 Baht per vehicle-km</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="3.978-4.212">
<comment><narrative>
3.978-4.212 Baht/v-km represent 10-15% reduction from baseline
</narrative></comment>
</target>
<actual value="4.52">
<comment><narrative>
Not updated as procurement of works on target roads is underway.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Average travel time reduced on widened sections by 20-30%
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="Total of 52.2-59.6 minutes of travel time on three widening sections (20-30% reduction)">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="53.60 minutes (avg 96.57 km/hr)">
<comment><narrative>
Achieved for the completed sections with original loan.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Three overpasses constructed at critical locations as per specifications
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="3">

</target>
<actual value="3">
<comment><narrative>
Achieved with original loan
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Number of fatalities reduced by 80% at improved locations
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="50 fatalities at 38 locations"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="10 fatalities at improved locations">
<comment><narrative>
Achieved
</narrative></comment>
</target>
<actual value="10 fatalities at improved locations">
<comment><narrative>
No more safety works have been carried out under the project since the update.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Average delays reduced at improved intersections by 60%
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="30.47 seconds average delay in three improved locations (60% reduction)">

</target>
<actual value="27.08 seconds average delay in three improved locations">
<comment><narrative>
No update as the works were completed.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
66 hazardous locations improved as per specifications
</narrative></title>
<baseline year="1900" iso-date="1900-01-01" value=""><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="1900-01-01" />
<period-end iso-date="2013-06-30" />
<target value="66">

</target>
<actual value="Over 100">
<comment><narrative>
Similar works are taken by DOH as routine.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Modern centralized database, road maintenance management system and bridge management system implemented and operational
</narrative></title>
<baseline year="2004" iso-date="2004-04-30" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-04-30" />
<period-end iso-date="2013-06-30" />
<target value="System operational">

</target>
<actual value="The bridge management system is being developed using DOH own funds">
<comment><narrative>
The bridge management system is being developed using DOH own funds.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Roads rehabilitated, Non-rural
</narrative></title>
<baseline year="2004" iso-date="2004-03-03" value="0.00"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-03" />
<period-end iso-date="2013-06-30" />
<target value="960.00">
<comment><narrative>
Achieved under original loan
</narrative></comment>
</target>
<actual value="1556.00">
<comment><narrative>
Achieved using conventional methods with SMEs
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Number of fatalities reduced by 80% at improved locations
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="50 fatalities at 38 locations"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="10 fatalities at improved locations">

</target>
<actual value="10 fatalities at improved locations">
<comment><narrative>
No more safety works have been carried out under the project since the update.
</narrative></comment>
</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PDO Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Asset value of road network increased by 0.2% by EOP       (or decline reversed)
</narrative></title>
<baseline year="2004" iso-date="2004-03-15" value="323.60"><comment><narrative>291.28 million Baht/km for maintenance project sections + 32.32 million Baht/ km for 3 widening projects</narrative></comment></baseline>
<period>
<period-start iso-date="2004-03-15" />
<period-end iso-date="2013-06-30" />
<target value="324.25">
<comment><narrative>
(324.25 Baht/km = Baseline + 0.2%)
</narrative></comment>
</target>
<actual value="331.62">
<comment><narrative>
Not updated as the additional civil works have not yet started.
</narrative></comment>
</actual>
</period>
</indicator>
</result></iati-activity><iati-activity xml:lang="en" default-currency="USD" last-updated-datetime="2026-11-20T19:29:57" hierarchy="1"><iati-identifier>44000-P509460</iati-identifier><reporting-org ref="44000" type="40"><narrative  xml:lang="en">World Bank</narrative></reporting-org><title xml:lang="en"><narrative>TRIP</narrative></title><description type="2" xml:lang="en"><narrative><![CDATA[]]></narrative></description><description type="1" xml:lang="en"><narrative><![CDATA[]]></narrative></description><participating-org role="1" ref="44001" type="40" xml:lang="en"><narrative>International Bank for Reconstruction and Development</narrative></participating-org><participating-org role="2" xml:lang="en" ref="TH–00009655"><narrative>Kingdom of Thailand</narrative></participating-org><participating-org role="3" ref="44001" type="40" xml:lang="en"><narrative>International Bank for Reconstruction and Development</narrative></participating-org><participating-org role="4" xml:lang="en" ref="TH-COA-00008989"><narrative>Department of Rural Roads</narrative></participating-org>
<activity-status code="2" /><activity-date type="1" iso-date="2025-12-22"><narrative>Planned start date of the activity</narrative></activity-date><activity-date type="2" iso-date="2025-12-22"><narrative>Actual start date of the activity</narrative></activity-date><activity-date type="3" iso-date="2030-12-20"><narrative>Planned end date of the activity</narrative></activity-date><activity-date type="2" iso-date="2030-12-20"><narrative>Projected end date of the activity</narrative></activity-date><contact-info type="1"><organisation><narrative>The World Bank</narrative></organisation><person-name><narrative>Chanin Manopiniwes</narrative></person-name><telephone>+1-202-473-1000</telephone><email>chanin@worldbankgroup.org</email><email>pic@worldbank.org</email><mailing-address><narrative>The World Bank, 1818 H Street, NW, Washington, DC 20433 USA</narrative></mailing-address></contact-info>




<recipient-country code="TH" percentage="100"><narrative xml:lang="en">THAILAND</narrative></recipient-country><location>
                <location-reach code="1" />
                <location-id vocabulary="G1" code="1609350" />
                <name><narrative>Bangkok</narrative></name>
                <point srsName="http://www.opengis.net/def/crs/EPSG/0/4326">
                <pos>13.75398 100.50144</pos>
                </point>
                <exactness code="2"/>
                <location-class code="2" />
            </location><sector vocabulary="1" code="21021" percentage="100" xml:lang="en"/><sector vocabulary="1" code="21021" percentage="100" xml:lang="en"/><sector vocabulary="99" vocabulary-uri="http://pubdocs.worldbank.org/en/538321490128452070/Sector-Taxonomy-and-definitions.pdf" code="TTI" percentage="100.000000" xml:lang="en"><narrative>Rural and Inter-Urban Roads</narrative></sector><collaboration-type code="2" /><default-aid-type code="C01" xml:lang="en"/><default-tied-status code="5" /><budget type="1" status="1">
<period-start iso-date="2025-12-01"/>
<period-end iso-date="2025-12-31"/>
<value currency="USD" value-date="2025-12-31">2142856.14</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-01-01"/>
<period-end iso-date="2026-01-31"/>
<value currency="USD" value-date="2026-01-31">2142856.14</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-02-01"/>
<period-end iso-date="2026-02-28"/>
<value currency="USD" value-date="2026-02-28">2142856.14</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-03-01"/>
<period-end iso-date="2026-03-31"/>
<value currency="USD" value-date="2026-03-31">2142856.14</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-04-01"/>
<period-end iso-date="2026-04-30"/>
<value currency="USD" value-date="2026-04-30">2142856.14</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-05-01"/>
<period-end iso-date="2026-05-31"/>
<value currency="USD" value-date="2026-05-31">2142856.14</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-06-01"/>
<period-end iso-date="2026-06-30"/>
<value currency="USD" value-date="2026-06-30">2142863.16</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-07-01"/>
<period-end iso-date="2026-07-31"/>
<value currency="USD" value-date="2026-07-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-08-01"/>
<period-end iso-date="2026-08-31"/>
<value currency="USD" value-date="2026-08-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-09-01"/>
<period-end iso-date="2026-09-30"/>
<value currency="USD" value-date="2026-09-30">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-10-01"/>
<period-end iso-date="2026-10-31"/>
<value currency="USD" value-date="2026-10-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-11-01"/>
<period-end iso-date="2026-11-30"/>
<value currency="USD" value-date="2026-11-30">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2026-12-01"/>
<period-end iso-date="2026-12-31"/>
<value currency="USD" value-date="2026-12-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-01-01"/>
<period-end iso-date="2027-01-31"/>
<value currency="USD" value-date="2027-01-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-02-01"/>
<period-end iso-date="2027-02-28"/>
<value currency="USD" value-date="2027-02-28">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-03-01"/>
<period-end iso-date="2027-03-31"/>
<value currency="USD" value-date="2027-03-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-04-01"/>
<period-end iso-date="2027-04-30"/>
<value currency="USD" value-date="2027-04-30">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-05-01"/>
<period-end iso-date="2027-05-31"/>
<value currency="USD" value-date="2027-05-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-06-01"/>
<period-end iso-date="2027-06-30"/>
<value currency="USD" value-date="2027-06-30">2500011.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-07-01"/>
<period-end iso-date="2027-07-31"/>
<value currency="USD" value-date="2027-07-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-08-01"/>
<period-end iso-date="2027-08-31"/>
<value currency="USD" value-date="2027-08-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-09-01"/>
<period-end iso-date="2027-09-30"/>
<value currency="USD" value-date="2027-09-30">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-10-01"/>
<period-end iso-date="2027-10-31"/>
<value currency="USD" value-date="2027-10-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-11-01"/>
<period-end iso-date="2027-11-30"/>
<value currency="USD" value-date="2027-11-30">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2027-12-01"/>
<period-end iso-date="2027-12-31"/>
<value currency="USD" value-date="2027-12-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-01-01"/>
<period-end iso-date="2028-01-31"/>
<value currency="USD" value-date="2028-01-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-02-01"/>
<period-end iso-date="2028-02-29"/>
<value currency="USD" value-date="2028-02-29">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-03-01"/>
<period-end iso-date="2028-03-31"/>
<value currency="USD" value-date="2028-03-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-04-01"/>
<period-end iso-date="2028-04-30"/>
<value currency="USD" value-date="2028-04-30">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-05-01"/>
<period-end iso-date="2028-05-31"/>
<value currency="USD" value-date="2028-05-31">4166665.67</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-06-01"/>
<period-end iso-date="2028-06-30"/>
<value currency="USD" value-date="2028-06-30">4166677.63</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-07-01"/>
<period-end iso-date="2028-07-31"/>
<value currency="USD" value-date="2028-07-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-08-01"/>
<period-end iso-date="2028-08-31"/>
<value currency="USD" value-date="2028-08-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-09-01"/>
<period-end iso-date="2028-09-30"/>
<value currency="USD" value-date="2028-09-30">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-10-01"/>
<period-end iso-date="2028-10-31"/>
<value currency="USD" value-date="2028-10-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-11-01"/>
<period-end iso-date="2028-11-30"/>
<value currency="USD" value-date="2028-11-30">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2028-12-01"/>
<period-end iso-date="2028-12-31"/>
<value currency="USD" value-date="2028-12-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-01-01"/>
<period-end iso-date="2029-01-31"/>
<value currency="USD" value-date="2029-01-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-02-01"/>
<period-end iso-date="2029-02-28"/>
<value currency="USD" value-date="2029-02-28">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-03-01"/>
<period-end iso-date="2029-03-31"/>
<value currency="USD" value-date="2029-03-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-04-01"/>
<period-end iso-date="2029-04-30"/>
<value currency="USD" value-date="2029-04-30">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-05-01"/>
<period-end iso-date="2029-05-31"/>
<value currency="USD" value-date="2029-05-31">2499999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-06-01"/>
<period-end iso-date="2029-06-30"/>
<value currency="USD" value-date="2029-06-30">2500011.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-07-01"/>
<period-end iso-date="2029-07-31"/>
<value currency="USD" value-date="2029-07-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-08-01"/>
<period-end iso-date="2029-08-31"/>
<value currency="USD" value-date="2029-08-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-09-01"/>
<period-end iso-date="2029-09-30"/>
<value currency="USD" value-date="2029-09-30">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-10-01"/>
<period-end iso-date="2029-10-31"/>
<value currency="USD" value-date="2029-10-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-11-01"/>
<period-end iso-date="2029-11-30"/>
<value currency="USD" value-date="2029-11-30">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2029-12-01"/>
<period-end iso-date="2029-12-31"/>
<value currency="USD" value-date="2029-12-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-01-01"/>
<period-end iso-date="2030-01-31"/>
<value currency="USD" value-date="2030-01-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-02-01"/>
<period-end iso-date="2030-02-28"/>
<value currency="USD" value-date="2030-02-28">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-03-01"/>
<period-end iso-date="2030-03-31"/>
<value currency="USD" value-date="2030-03-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-04-01"/>
<period-end iso-date="2030-04-30"/>
<value currency="USD" value-date="2030-04-30">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-05-01"/>
<period-end iso-date="2030-05-31"/>
<value currency="USD" value-date="2030-05-31">999999.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-06-01"/>
<period-end iso-date="2030-06-30"/>
<value currency="USD" value-date="2030-06-30">1000011.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-07-01"/>
<period-end iso-date="2030-07-31"/>
<value currency="USD" value-date="2030-07-31">1293332.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-08-01"/>
<period-end iso-date="2030-08-31"/>
<value currency="USD" value-date="2030-08-31">1293332.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-09-01"/>
<period-end iso-date="2030-09-30"/>
<value currency="USD" value-date="2030-09-30">1293332.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-10-01"/>
<period-end iso-date="2030-10-31"/>
<value currency="USD" value-date="2030-10-31">1293332.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-11-01"/>
<period-end iso-date="2030-11-30"/>
<value currency="USD" value-date="2030-11-30">1293332.33</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-12-01"/>
<period-end iso-date="2030-12-31"/>
<value currency="USD" value-date="2030-12-31">1293338.35</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2025-12-01"/>
<period-end iso-date="2025-12-31"/>
<value currency="USD" value-date="2025-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-01-01"/>
<period-end iso-date="2026-01-31"/>
<value currency="USD" value-date="2026-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-02-01"/>
<period-end iso-date="2026-02-28"/>
<value currency="USD" value-date="2026-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-03-01"/>
<period-end iso-date="2026-03-31"/>
<value currency="USD" value-date="2026-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-04-01"/>
<period-end iso-date="2026-04-30"/>
<value currency="USD" value-date="2026-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-05-01"/>
<period-end iso-date="2026-05-31"/>
<value currency="USD" value-date="2026-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-06-01"/>
<period-end iso-date="2026-06-30"/>
<value currency="USD" value-date="2026-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-07-01"/>
<period-end iso-date="2026-07-31"/>
<value currency="USD" value-date="2026-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-08-01"/>
<period-end iso-date="2026-08-31"/>
<value currency="USD" value-date="2026-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-09-01"/>
<period-end iso-date="2026-09-30"/>
<value currency="USD" value-date="2026-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-10-01"/>
<period-end iso-date="2026-10-31"/>
<value currency="USD" value-date="2026-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-11-01"/>
<period-end iso-date="2026-11-30"/>
<value currency="USD" value-date="2026-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2026-12-01"/>
<period-end iso-date="2026-12-31"/>
<value currency="USD" value-date="2026-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-01-01"/>
<period-end iso-date="2027-01-31"/>
<value currency="USD" value-date="2027-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-02-01"/>
<period-end iso-date="2027-02-28"/>
<value currency="USD" value-date="2027-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-03-01"/>
<period-end iso-date="2027-03-31"/>
<value currency="USD" value-date="2027-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-04-01"/>
<period-end iso-date="2027-04-30"/>
<value currency="USD" value-date="2027-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-05-01"/>
<period-end iso-date="2027-05-31"/>
<value currency="USD" value-date="2027-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-06-01"/>
<period-end iso-date="2027-06-30"/>
<value currency="USD" value-date="2027-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-07-01"/>
<period-end iso-date="2027-07-31"/>
<value currency="USD" value-date="2027-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-08-01"/>
<period-end iso-date="2027-08-31"/>
<value currency="USD" value-date="2027-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-09-01"/>
<period-end iso-date="2027-09-30"/>
<value currency="USD" value-date="2027-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-10-01"/>
<period-end iso-date="2027-10-31"/>
<value currency="USD" value-date="2027-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-11-01"/>
<period-end iso-date="2027-11-30"/>
<value currency="USD" value-date="2027-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2027-12-01"/>
<period-end iso-date="2027-12-31"/>
<value currency="USD" value-date="2027-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-01-01"/>
<period-end iso-date="2028-01-31"/>
<value currency="USD" value-date="2028-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-02-01"/>
<period-end iso-date="2028-02-29"/>
<value currency="USD" value-date="2028-02-29">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-03-01"/>
<period-end iso-date="2028-03-31"/>
<value currency="USD" value-date="2028-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-04-01"/>
<period-end iso-date="2028-04-30"/>
<value currency="USD" value-date="2028-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-05-01"/>
<period-end iso-date="2028-05-31"/>
<value currency="USD" value-date="2028-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-06-01"/>
<period-end iso-date="2028-06-30"/>
<value currency="USD" value-date="2028-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-07-01"/>
<period-end iso-date="2028-07-31"/>
<value currency="USD" value-date="2028-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-08-01"/>
<period-end iso-date="2028-08-31"/>
<value currency="USD" value-date="2028-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-09-01"/>
<period-end iso-date="2028-09-30"/>
<value currency="USD" value-date="2028-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-10-01"/>
<period-end iso-date="2028-10-31"/>
<value currency="USD" value-date="2028-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-11-01"/>
<period-end iso-date="2028-11-30"/>
<value currency="USD" value-date="2028-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2028-12-01"/>
<period-end iso-date="2028-12-31"/>
<value currency="USD" value-date="2028-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-01-01"/>
<period-end iso-date="2029-01-31"/>
<value currency="USD" value-date="2029-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-02-01"/>
<period-end iso-date="2029-02-28"/>
<value currency="USD" value-date="2029-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-03-01"/>
<period-end iso-date="2029-03-31"/>
<value currency="USD" value-date="2029-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-04-01"/>
<period-end iso-date="2029-04-30"/>
<value currency="USD" value-date="2029-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-05-01"/>
<period-end iso-date="2029-05-31"/>
<value currency="USD" value-date="2029-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-06-01"/>
<period-end iso-date="2029-06-30"/>
<value currency="USD" value-date="2029-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-07-01"/>
<period-end iso-date="2029-07-31"/>
<value currency="USD" value-date="2029-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-08-01"/>
<period-end iso-date="2029-08-31"/>
<value currency="USD" value-date="2029-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-09-01"/>
<period-end iso-date="2029-09-30"/>
<value currency="USD" value-date="2029-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-10-01"/>
<period-end iso-date="2029-10-31"/>
<value currency="USD" value-date="2029-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-11-01"/>
<period-end iso-date="2029-11-30"/>
<value currency="USD" value-date="2029-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2029-12-01"/>
<period-end iso-date="2029-12-31"/>
<value currency="USD" value-date="2029-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-01-01"/>
<period-end iso-date="2030-01-31"/>
<value currency="USD" value-date="2030-01-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-02-01"/>
<period-end iso-date="2030-02-28"/>
<value currency="USD" value-date="2030-02-28">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-03-01"/>
<period-end iso-date="2030-03-31"/>
<value currency="USD" value-date="2030-03-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-04-01"/>
<period-end iso-date="2030-04-30"/>
<value currency="USD" value-date="2030-04-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-05-01"/>
<period-end iso-date="2030-05-31"/>
<value currency="USD" value-date="2030-05-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-06-01"/>
<period-end iso-date="2030-06-30"/>
<value currency="USD" value-date="2030-06-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-07-01"/>
<period-end iso-date="2030-07-31"/>
<value currency="USD" value-date="2030-07-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-08-01"/>
<period-end iso-date="2030-08-31"/>
<value currency="USD" value-date="2030-08-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-09-01"/>
<period-end iso-date="2030-09-30"/>
<value currency="USD" value-date="2030-09-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-10-01"/>
<period-end iso-date="2030-10-31"/>
<value currency="USD" value-date="2030-10-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-11-01"/>
<period-end iso-date="2030-11-30"/>
<value currency="USD" value-date="2030-11-30">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-12-01"/>
<period-end iso-date="2030-12-31"/>
<value currency="USD" value-date="2030-12-31">0.00</value>
</budget>
<budget type="2" status="1">
<period-start iso-date="2030-12-01"/>
<period-end iso-date="2030-12-20"/>
<value currency="USD" value-date="2030-12-20">140760000.00</value>
</budget>
<budget type="1" status="1">
<period-start iso-date="2030-12-01"/>
<period-end iso-date="2030-12-20"/>
<value currency="USD" value-date="2030-12-20">140760000.00</value>
</budget>
<capital-spend percentage="100" /><transaction><transaction-type code="2" /><transaction-date iso-date="2025-12-31"/><value value-date="2025-12-31">101780300</value><description xml:lang="en"><narrative>Total Commitment in December Month of 2025</narrative></description><provider-org ref="44001"><narrative>International Bank for Reconstruction and Development</narrative></provider-org><receiver-org xml:lang="en" ref="TH-COA-9656"><narrative>Department of Marine and Coastal Resources; Department of Rural Roads</narrative></receiver-org><flow-type code="20" /><finance-type code="410" /></transaction>
<transaction><transaction-type code="2" /><transaction-date iso-date="2025-12-31"/><value value-date="2025-12-31">38979700</value><description xml:lang="en"><narrative>Total Commitment in December Month of 2025</narrative></description><provider-org ref="44001"><narrative>International Bank for Reconstruction and Development</narrative></provider-org><receiver-org xml:lang="en" ref="TH-COA-9656"><narrative>Department of Marine and Coastal Resources; Department of Rural Roads</narrative></receiver-org><flow-type code="20" /><finance-type code="410" /></transaction>
<transaction><transaction-type code="3" /><transaction-date iso-date="2026-10-31"/><value value-date="2026-10-31">0</value><description xml:lang="en"><narrative>Total Disbursement in October Month of 2026</narrative></description><provider-org ref="44001"><narrative>International Bank for Reconstruction and Development</narrative></provider-org><receiver-org xml:lang="en" ref="TH-COA-9656"><narrative>Department of Marine and Coastal Resources; Department of Rural Roads</narrative></receiver-org><flow-type code="20" /><finance-type code="410" /></transaction>
<document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-procurement/P509460"><title xml:lang="en"><narrative>Contract Awards</narrative></title><category code="A11" /></document-link><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-detail/P509460?lang=en"><title xml:lang="en"><narrative>Project URL</narrative></title><category code="A12" /></document-link><document-link format="text/html" url="https://projects.worldbank.org/en/projects-operations/project-procurement/P509460"><title xml:lang="en"><narrative>Procurement Notices</narrative></title><category code="A10" /></document-link><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="160">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="350,000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Population living in districts directly benefitting from the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-14" />
<target value="500000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
People with improved access to emergency evacuation during climate events
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-14" />
<target value="90000">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Human-caused mortalities of Irrawaddy dolphins in Thale Luang
</narrative></title>
<baseline year="2024" iso-date="2024-12-14" value="3"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2024-12-14" />
<period-end iso-date="2030-12-15" />
<target value="0">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Key research studies on Thale Luang ecosystem are used to prepare policy proposals for mitigation
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="Research studies not available"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="Policy proposals prepared and submitted to MONRE">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Grievances registered and addressed in a timely manner
</narrative></title>
<baseline year="2025" iso-date="2025-10-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-14" />
<period-end iso-date="2030-12-14" />
<target value="80">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
People with improved access to emergency evacuation during climate events
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="90000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Key research studies on Thale Luang ecosystem are used to prepare policy proposals for mitigation
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="Research studies not available"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="Policy proposals prepared and submitted to MONRE">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="500000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Grieveances registered and addressed in a timely manner
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="80">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Fishing communities around Thale Luang with budgets allocated to manage their conservation and livelihood development sub-projects
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="20">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Key research studies on Thale Luang ecosystem are used to prepare policy proposals for mitigation
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="Research studies not available"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="Policy proposals prepared and submitted to MONRE">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Road constructed
</narrative></title>
<baseline year="2025" iso-date="2025-10-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-14" />
<period-end iso-date="2030-12-14" />
<target value="9">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Fishing communities around Thale Luang with budgets allocated to manage their conservation and livelihood development sub-projects
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="20">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Road constructed
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2029-12-11" />
<target value="9.2">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Fishing communities around Thale Luang with budgets allocated to manage their conservation and livelihood development sub-projects
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="20">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Women network to conserve Irrawaddy dolphins is established
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="350,000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Core and buffer zone boundaries under the new Thale Luang NHA zoning are demarcated and communicated to stakeholders
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Beneficiaries expressing satisfaction with improved accessibility due to the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="70">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Official survey with abundance estimate of Irrawaddy dolphins in Thale Luang completed and published bi-annually
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Human-caused mortalities of Irrawaddy dolphins in Thale Luang
</narrative></title>
<baseline year="2024" iso-date="2024-12-14" value="3"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2024-12-14" />
<period-end iso-date="2030-12-15" />
<target value="0">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
People with improved access to emergency evacuation during climate events
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="90000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Women network to conserve Irrawaddy dolphins is established
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Human-caused mortalities of Irrawaddy dolphins in Thale Luang
</narrative></title>
<baseline year="2024" iso-date="2024-12-14" value="3"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2024-12-14" />
<period-end iso-date="2030-12-15" />
<target value="0">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
People with improved access to emergency evacuation during climate events
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-14" />
<target value="90000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Grieveances registered and addressed in a timely manner
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="80">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Human-caused mortalities of Irrawaddy dolphins in Thale Luang
</narrative></title>
<baseline year="2024" iso-date="2024-12-14" value="3"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2024-12-14" />
<period-end iso-date="2030-12-15" />
<target value="0">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Core and buffer zone boundaries defined by the Thale Luang NHA management plan demarcated and communicated to stakeholders
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Population living in districts directly benefitting from the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-14" />
<target value="500000">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Official survey with abundance estimate of Irrawaddy dolphins in Thale Luang completed and published bi-annually
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="160">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Road constructed
</narrative></title>
<baseline year="2025" iso-date="2025-10-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-14" />
<period-end iso-date="2030-12-14" />
<target value="9">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Official survey with abundance estimate of Irrawaddy dolphins in Thale Luang completed and published bi-annually
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="No">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Core and buffer zone boundaries under the new Thale Luang NHA zoning are demarcated and communicated to stakeholders
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="No">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Women network to conserve Irrawaddy dolphins is established
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Road constructed
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="9">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Core and buffer zone boundaries under the new Thale Luang NHA zoning are demarcated and communicated to stakeholders
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="160">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Fishing communities around Thale Luang with budgets allocated to manage their conservation and livelihood development sub-projects
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="20">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Beneficiaries expressing satisfaction with improved accessibility due to the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="70">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="350,000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Reduction in travel time
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="160"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="25">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Population living in districts directly benefitting from the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="500000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Women network to conserve Irrawaddy dolphins is established
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="No">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Beneficiaries expressing satisfaction with improved accessibility due to the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-14" />
<target value="70">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Official survey with abundance estimate of Irrawaddy dolphins in Thale Luang completed and published bi-annually
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="No"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="Yes">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Grievances registered and addressed in a timely manner
</narrative></title>
<baseline year="2025" iso-date="2025-10-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-14" />
<period-end iso-date="2030-12-14" />
<target value="80">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="5" ascending="1">
<title><narrative>
Key research studies on Thale Luang ecosystem are used to prepare policy proposals for mitigation
</narrative></title>
<baseline year="2025" iso-date="2025-09-15" value="Research studies not available"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-15" />
<period-end iso-date="2030-12-15" />
<target value="Policy proposals prepared and submitted to MONRE">

</target>
<actual value="Research studies not available">

</actual>
</period>
</indicator>
</result><result type="1" aggregation-status="0">
<title><narrative>
IO - Intermediate Results Indicator 
</narrative></title>
<indicator measure="2" ascending="1">
<title><narrative>
Beneficiaries expressing satisfaction with improved accessibility due to the bridges
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-14" />
<target value="70">

</target>
<actual value="0">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Landscapes under enhanced conservation and/or sustainable management (terrestrial and inland water areas)
</narrative></title>
<baseline year="2025" iso-date="2025-09-14" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-09-14" />
<period-end iso-date="2030-12-14" />
<target value="78,200">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result><result type="2" aggregation-status="0">
<title><narrative>
PD -Project Development Objectives 
</narrative></title>
<indicator measure="1" ascending="1">
<title><narrative>
Direct users that benefit from improved access to sustainable transport infrastructure and services
</narrative></title>
<baseline year="2025" iso-date="2025-10-15" value="0"><comment><narrative></narrative></comment></baseline>
<period>
<period-start iso-date="2025-10-15" />
<period-end iso-date="2030-12-15" />
<target value="520,0000">

</target>
<actual value="">

</actual>
</period>
</indicator>
</result></iati-activity></iati-activities>